问题:

The communication management plan determines the information and communications needs of the stakeholders. In the following statements related to communication management plan. ( ) is false.A.The communication management plan is contained in or is A.subsidiary plan of, the project management plan.
A:The communication management plan can be formal or informal, highly detaile
B:or broadly framed, and based on the needs of the project.
C:The communication manamgement plan organize and summarize the information gathered, and present the results of any analysis as comparedthe performance measurement baseline.
D:The communication management plan can include guidelines project status meetings, project team meetings, e-meetines, and e-mail.

答案:


解析:


相关标签:

(高级)信息系统项目管理师     communications     communication     information     项目管理     determines    

热门排序

推荐文章

认真阅读以下关于网页制作和网页编程的内容,回答问题1至问题5,将解答填入答题纸对应的解答栏内。【说明】  某电子商务公司用ASP 实现了一个用于手机信息查询的程序,主页文件名为"index.asp", EDI系统格式转换的第一步是将单证数据转换为( )。 某系统集成A公司中标了一个地铁综合监控系统项目,该项目是地铁运营公司公开招标的地铁S号线建设项目中的一个信息系统子项目,涉及信号系统、电气控制系统、广播系统、视频监控系统、通信网络系统的信息互通和集中 估计一个项目所需时间常有乐观估计时间、最可能时间和悲观估计时间。根据这三个时间的加权平均(权为常数)可以推算出这个项目的期望时间。下表中,项目3的期望时间大致是( )天。 "http://www.sina.com.cn"中,"( )"属于组织和地理性域名A.sina.com 区块链2.0技术架构自上而下分为数据层、网络层、共识层、激励层、智能合约层,数据传播机制、数据验证机制属于其中的 ( ) 。 某项目经理在定义项目范围时绘制了如下所示的WBS。根据该图,下列说法中, ( ) 是不正确的。 操作系统的主要功能是__( )__。 某计算机系统由下图所示的部件构成,假定每个部件的千小时可靠度为R,则该系统的千小时可靠度为( )。 以下关于TCP/IP 协议和层次对应关系的表示,正确的是( )。
221381
领取福利

微信扫码领取福利

微信扫码分享